PERT gives a weighted expected duration and a rough sigma from O/M/P.
Estimation
PERT gives a weighted expected duration and a rough sigma from O/M/P.
Enter O ≤ M ≤ P to get TE and confidence intervals.
Guide
PERT gives a weighted expected duration and a rough sigma from O/M/P.
Single-point estimates are usually optimistic.
Enter O ≤ M ≤ P to get TE and confidence intervals.
Formula: TE = (O + 4M + P) ÷ 6 · σ = (P − O) ÷ 6
Go deeper
Single-point estimates are usually optimistic — use three points.
Keep O ≤ M ≤ P.
Expected time and spread.
Rough 68% and 95% ranges.
Replace one hopeful number.
See the O-to-P gap.
Feed TE into project plans.
Any consistent unit (hours/days).
A common engineering approximation, not a formal hypothesis test.